Project Details

Automobile Shredder

Project started in September 1999
Project completed in February 2000
Project Type: Industrial
Owner: Seattle Iron & Metal Corp.
Location: Seattle, WA
Contract Amount: $0.4 Million
Designer: Texas Shredder, Inc.
 

The shredder process line consisted of five major elements of equipment: infeed conveyor system, shredder machinery, ferrous metals separation equipment, non-ferrous materials separation equipment and debris separation machinery. All these elements were connected by a series of conveyors. Associated piping for water, pneumatics and hydraulics were also installed.

 