Project Details
Bangor Fox Island Lab Relocation
Project started in June 2007
Project completed in January 2008
Project Type: Marine
Owner: US Navy
Location: Bangor, WA
Contract Amount: $1.5 Million
Designer: Winzler & Kelly
General Construction Company was a subcontractor to Watts Constructors for the construction of an acoustics testing facility located at Bangor Subase on the Kitsap Peninsula in Washington. The facility was built on a floating pontoon the Navy purchased. Generals scope of work consisted of constructing the approach trestle, eight mooring dolphins for the pontoon, and mooring the pontoon with assistance from the Navy. A total of 20 trestle piles and 40 dolphin piles were driven, 4 precast and 2 cast in place trestle pile caps were installed, 25 channel beams for trestle deck were installed, 8 dolphin pile tops were formed and poured, and a mooring pontoon was constructed.
__________________________________________________________
This page was generated on 9/7/2010.
< Show most current projects
< Back
< Go to the Search
< Print
|