Structures that last are built on strong foundations. For General Construction, that's not just an engineering principle, it's our business philosophy.

Project Details

Revelstoke Penstock Project

Project began November 2007
Expected Completion is May 2010
Project Type: Heavy Civil
Owner: British Columbia Hydro
Location: Revelstoke, BC
Contract Amount: $33.2 Million
Designer: British Columbia Hydro
 

General Construction Company and Kiewits Western Canada District formed a Joint Venture partnership for the installation of a fifth penstock at Revelstoke Dam in British Columbia. The penstock is approximately 250 ft. long and connects the reservoir to a turbine unit via a 26 ft. diameter steel pipe. Kiewits Western Canada is also responsible for all concrete incasing the generator unit. The turbine generator unit at the base of the dam is being installed under a separate contract, by Voith Seimens.

 

__________________________________________________________
This page was generated on 9/7/2010.
< Show most current projects
< Back
< Go to the Search
 

< Print