Factory Seismic Upgrade

Project started in 1997
Project completed September 2002
Project Type: Industrial
Owner: Confidential Manufacturing Company
Location: Everett, WA
Contract Amount: $57 Million
Designer: The Austin Group
 

 

This project upgraded the assembly facility's ability to withstand seismic forces. General Construction installed 2,000-tons of steel and 4,000 structural connections as high as 120 ft above ground. The entire project was accomplished with no interruption to production.

 