Listed below are all projects. To view details
for each project, please click the project name.
 |
Alameda Channel Maintenance Dredging
Project started August 2008 - Project completion was November 2008
General Construction Company was contracted for the Alameda maintenance channel dredging in California. |
 |
 |
Allen Street Bridge Replacement
Project started in 1999 - Project completed in 2001
Replacement of two lane, multi-span steel truss bridge originally built in 1923. |
 |
 |
Anacortes Ferry Terminal Slip 2 Refurbishment, Slips 1 & 2 Dolphins
Project started in 2001 - Project completed in 2002
Refurbishment of Anacortes ferry terminal slips. |
 |
 |
Automobile Shredder
Project started in September 1999 - Project completed in February 2000
Installation of a state of the art automobile shredder for recycling automobiles into scrap steel. |
 |
 |
Bainbridge Island Ferry Terminal
Project started in 2005 - Project completed in 2006
General Construction demolished the existing ferry terminal slip and constructed new slip. |
 |
 |
Bainbridge Island Ferry Terminal Dolphin Replacement Phase II
Project started in 2001 - Project completed in 2002
General Construction replaced of Bainbridge Island ferry terminal dolphins. |
 |
 |
Bangor Building 7111 Addition & Service Pier Upgrade
Project started in 2004 - Project completed in 2005
General Construction was responsible for upgrading existing service pier and facility to accommodate a new submarine homeport. |
 |
 |
Bangor Fox Island Lab Relocation
Project started in June 2007 - Project completed in January 2008
This project included the construction of a concrete trestle supported by twenty steel piles. |
 |
 |
Benicia Segmental Bridge
Project started in 2001 - Project was completed August 2007
Construction of a five lane segmental concrete bridge spanning the Carquinez Strait. |
 |
 |
Bonneville Dam Juvenile Fish Bypass System Outfalls
Project started in 1998 - Project completed in 1999
Two juvenile fish bypass outfalls in the Columbia River downstream of Bonneville Dam were installed. |
 |
 |
Chevron Long Wharf Causeway/Trestle Seismic Upgrade
Project started in 1998 - Project completed in 2000
This project included seismically strengthening the 3,800 ft, two lane concrete causeway as well as replacing a timber pipe trestle that paralleled the existing concrete causeway with a new steel trestle. |
 |
 |
Compressed Air Upgrades
Project started in October 2004 - Project completed in December 2004
This project included installation of a new 3,000 CFM air compressor. |
 |
 |
Continuous Homogenizing Furnace
Project started in June 1998 - Project completed in December 1998
The objective of this project was to replace an existing aluminum billet homogenizing system with a state-of-the-art fully automatic continuous homogenizing system. |
 |
 |
Crane Upgrade
Project started in 1999 - Project completed in 2003
This program upgraded the overhead bridge cranes in five assembly buildings at customer's Renton plant. |
 |
 |
Day Island Marina
Project started July 2008 - Project completed September 2008
General Construction Company maintenance-dredged the Day Island Harbor Marina in University Place, WA. |
 |
 |
Electric Boat Graving Dock 3
January 2005 - February 2006
This project included construction of tied-back concrete retaining walls in front of the existing sheetpile wall. |
 |
 |
Electric Boat Graving Docks 1 & 2
Project started in September, 2006 - Project finished April 2008
This project consisted of long term repair of Graving Docks #1 & 2, in which building reinforced and thru-tied concrete walls on the basin and docks occurred. |
 |
 |
Everett Factory Realignment
Project started in 2006 - Project completed in 2007
Conversion of 170,000 sq ft of manufacturing space into office facilities. |
 |
 |
Factory Seismic Upgrade
Project started in 1997 - Project completed September 2002
General Construction structurally reinforced client's assembly facility in Everett. |
 |
 |
Hamilton Avenue Bascule Bridge Project
Project started in August 2005 - Project completed in 2009
This project included the rehabilitation of the Hamilton Avenue Bascule Bridge over the Gowns Canal in Brooklyn, NY. |
 |
 |
Heating System Upgrade
Started in November 2006 - Completed January 2007
General Construction replaced the majority of the mechanical fittings on the existing heating system's carbon steel pipes with welded fittings. |
 |
 |
Homer M. Hadley Bridge Repair
Project will start May 2009 - Project completion anticipated July 2009
General Construction Company replaced four expansion joints on the Homer M. Hadley Bridge, I-90. |
 |
 |
Ice Harbor Navigation Coffer Cells
Project started in 1996 - Project completed in 1997
Spillway deflectors were installed at eight of the Ice Harbor Dam's ten spillways. |
 |
 |
John Day Dam Flow Deflectors
Project started in 1996 - Project completed in 1998
General Construction contract was to build 17 pier extensions and 18 flow deflectors 30 ft underwater along the spillway face of the dam. |
 |
 |
Keyport Pier Replacement
Project started in 2000 - Project completed in 2002
This design build project consists of a modern pier and new floating structures to accommodate research vessels at the Keyport Undersea Warfare Research Station. |
 |
 |
Kingston Ferry Terminal Phase II Dolphin Replacements
Project started in 2001 - Project completed in 2002
General Construction replaced the dolphins at Kingston ferry terminal. |
 |
 |
Kingston Outfall
Project started in June 2004 - Project completed in October 2007
This project required the installation of one mile of 18 in. steel outfall pipe adjacent to the ferry landing in Kingston, WA. |
 |
 |
Lake Youngs Intake
Project started in 2002 - Project completed in 2003
This intake pier, for an active drinking water reservoir, required 500-tons of fabricated steel, piles and four piers supporting a pump platform. |
 |
 |
Lopez Island Ferry Terminal
Project started August 2006 - Completed December 2007
This project provided for the preservation of the Lopez Ferry Terminal in San Juan County, Washington. |
 |
 |
Marine Docking Facility, U.S. Gypsum
Project started in January, 2000 - Project completed in July 2000
Along the Columbia River in Oregon, General Construction built a concrete wharf and concrete approach trestle. |
 |
 |
Midway Sewer District Submarine Outfall
Project started in June 2007 - Project completed in January 2008
This project included the installation of 2,100 ft of 48 in. steel outfall pipe to the diffuser section which runs to a depth of -170 MMLW. |
 |
 |
Napkin Packaging Line Installation
Project started in September 2004 - Project completed in February 2005
General Construction installed a converting and packaging production line at a paper manufacturing mill. |
 |
 |
Navigation and Sediment Dredging, Puget Sound Naval Shipyard
Project started in 2000 - Project completed in 2001
This project was a large scale environmental dredging at Bremerton's Naval Shipyard in Washington. |
 |
 |
Neah Bay Coast Guard Pier
Project started in 1999 - Project completed in 2000
This project required the demolition of an existing 650 ft timber pier and construction of a new concrete pier and concrete mooring floats. |
 |
 |
Norfolk Sediment Remediation
Project started in January 1999 - Project completed in April 1999
This project was part of the Elliot Bay/Duwamish dredging and restoration. |
 |
 |
Orleans Outfall Canal Interim Closure Structure
Project started in February 2006 - Project completed in December 2006
General Construction was a participating Kiewit district that aided in the construction of an interim gated flood control structure on the canal at Lake Pontchartrain. |
 |
 |
Paper Machine Drive Upgrade
Project started in January 2005 - Project completed in November 2005
General Construction replaced all 42 DC motors in a tissue machine at paper manufacturing facility in Washington. |
 |
 |
Paper Machine Fan Pump Drives
Project started in January 2004 - Project completed in March 2004
General Construction Company replaced the drives, cabling and motors for three 600 Hp fan pumps at a paper manufacturing facility in Washington. |
 |
 |
Pier 23 Replacement Project
Project starts July 2009 - Project will finish May 2011
This contract is for the removal and replacement of 600 feet of pier in Tacoma, WA. |
 |
 |
Pier D Replacement
Project started in 2000 - Project completed in 2003
This design build project consisting of building a 1350 x 150 carrier berthing pier at the Naval Station in Bremerton. |
 |
 |
Pierce County Terminal Expansion
Project started in 2002 - Project completed in 2003
This project consisted of dredging and habitat construction at the Pierce County Slip 5 Terminal in Tacoma, WA. |
 |
 |
Port of Anchorage Maintenance Dredging
- Project completed in November 2002
General Construction did massive maintenance dredging at the Port of Anchorage in Alaska. |
 |
 |
Post Point Alternative Outfall
Project started September 2007 - Project completed September 2007
General worked as a subcontractor to Strider Construction for this outfall project in Bellingham, WA. |
 |
 |
Priest Rapids Dam Fish Bypass
Project started in September 2005 - Project completed in March 2006
General Construction modified two existing spillways for fish bypass. |
 |
 |
Production Line Hydraulic System
Project started mid 2006 - Project completed July 2007
General Construction furnished and installed this system, which supplies hydraulics to the assembly line. |
 |
 |
Relocate and Upgrade Tissue Packaging Line
Project started in October 2005 - Project completed in February 2006
For this project General Construction moved and upgraded a production line which converts very large rolls of tissue to finished product. |
 |
 |
Replace Fendering System at Pier 7
June 2008 - Anticipated completion November 2008
General Construction removed and replaced the fender system at Pier 7 in Bremerton. |
 |
 |
San Francisco - Oakland Bay Bridge E2/T1 Foundation
Project started April 2004 - Completed March 2008
As part of a KFM joint venture, General Construction built two foundations for the main span of the future self anchored suspension span of the San Francisco Oakland Bay Bridge. |
 |
 |
San Francisco - Oakland Bay Bridge, Skyway Segment
Project started in 2002 - Project completion 2008
The $1.2 billion Skyway Segment of the San Francisco-Oakland Bay Bridge project included the construction of a mile and a half of side-by-side viaduct bridge structures in San Francisco Bay. |
 |
 |
Shilshole Marina
Project started in 1996 - Project completed in 1998
At Shilshole Marina, General Construction demolished an old pier and construction a new 600 lin ft pier. |
 |
 |
Skylight Installation Project
Project began in October 2007 - Projected completed December 2008
This project included the installation of giant 25 ft x 27 ft skylights in a huge manufacturing facility in Everett. |
 |
 |
South Bay Ocean Outfall
Project started January of 1996 - Project completed January 1998
The South Bay Ocean Outfall is the final segment of a wastewater treatment facility designed to collect and treat sewage from Tijuana, Mexico. |
 |
 |
SR520 Pontoon Construction
Project started in December 2010 - Anticipated completion date is March 2014
Kiewit-General will begin construction of a new casting facility in Aberdeen, WA. Once the casting facility is complete, Kiewit-General will start building the SR520 Floating Bridge pontoons. |
 |
 |
Stacker Crane Replacement
Project started in April 2007 - Project finished September 2007
This project included the installation of approximately 3,500 lin ft of crane rail. |
 |
 |
Substation Replacement & Power System Upgrades
Project started in January 2004 - Project completed in July 2004
General Construction was responsible for building a new substation at paper manufacturing facility. |
 |
 |
Switchgear Relocation
Project started in 2006 - Project completed in 2007
This project included the relocation of a new primary 15kV distribution system and switchgear. |
 |
 |
Tacoma Narrows Bridge
Began July 2004 - Finished March 2008
General Construction Company was part of the team who constructed a 5,200 ft suspension bridge adjacent to the existing bridge in Tacoma, WA. |
 |
 |
Terminal 115, Port of Seattle
Project began October 2006 - Project completed April 2008
General Construction reconstructed and upgraded one of the largest break bulk barge facility in the Western Hemisphere. |
 |
 |
Terminal 3 & 4, Port of Tacoma
Project started in January 2005 - Project completed in March 2006
This project included the construction of a 250 lin ft concrete wharf at the Port of Tacoma. |
 |
 |
Terminal 30 Upgrade, Port of Seattle
Project started October 2007 - Projected completion date June 2009
The 43-acre Terminal 30 Upgrade project included relocation of the Cruise Ship operation, and returning the terminal to its original function as a container terminal. |
 |
 |
Terminal 55/56, Port of Oakland
Project started in 1999 - Project completed in 2001
This project included the demolishing of existing concrete piers, hydraulic dredging and construction of a new wharf. |
 |
 |
Terminal 91 Berth M Reconstruction, Port of Seattle
Project began October 2007 - Completed June 2008
This project included the demolition of the old timber apron and supporting piles and construction of a new dock supported with concrete and sheet piles. |
 |
 |
Tissue Machine Rebuild
Project started in November 2005 - Project completed in January 2006
General Construction replaced and relocated paper rolls, the drying air system, two 9 MM BTU burners and a Smartfire control system. |
 |
 |
Tissue Paper Machine 3 Rebuild
- Project completed in 1997
This project included the installation of a new head box, Yankee dryer hood with burners and gas train, drives, vacuum system, pumps, piping, pressure screen, showers and control system. |
 |
 |
Todd Shipyard Sediment Remediation Project
Project started in 2004 - Project completed in 2005
General Construction dredged 203,000 cu yd of contaminated sediment that was then trans-loaded into railcars for upland disposal. |
 |
 |
Wanapum Dam Fish Bypass
June 2005 - Completed April 2008
General Construction constructed a new fish bypass spillway at Wanapum Dam, located on the Columbia River near Vantage, WA. |
 |
 |
Yaquina North Jetty Rock Removal
Project started in July 1999 - Project completed in September 1999
General Construction rebuilt the Yaquina North Jetty in Oregon. |
 |