 |
Bonneville Dam Juvenile Fish Bypass System Outfalls
Project started in 1998 - Project completed in 1999
Two juvenile fish bypass outfalls in the Columbia River downstream of Bonneville Dam were installed. |
 |
 |
Ice Harbor Navigation Coffer Cells
Project started in 1996 - Project completed in 1997
Spillway deflectors were installed at eight of the Ice Harbor Dam's ten spillways. |
 |
 |
John Day Dam Flow Deflectors
Project started in 1996 - Project completed in 1998
General Construction contract was to build 17 pier extensions and 18 flow deflectors 30 ft underwater along the spillway face of the dam. |
 |
 |
Priest Rapids Dam Fish Bypass
Project started in September, 2005 - Project completed in March, 2006
General Construction modified two existing spillways for fish bypass. |
 |
 |
Revelstoke Penstock Project
Project began November 2007 - Expected Completion is November 2008
As a joint venture with Kiewit's Western Canada District, General Construction Company is installing the fifth penstock at Revelstoke Dam in Canada. |
 |
 |
Wanapum Dam Fish Bypass
Currently in construction - Scheduled to finish in 2008
General Construction is in the process of constructing a new fish bypass spillway at Wanapum Dam, located on the Columbia River near Vantage, WA. |
 |