Compressed Air Upgrades
Project started in October 2004 - Project completed in December 2004
This project included installation of a new 3,000 CFM air compressor. |
 |
 |
Paper Machine Drive Upgrade
Project started in January 2005 - Project completed in November 2005
General Construction replaced all 42 DC motors in a tissue machine at paper manufacturing facility in Washington. |
 |
 |
Relocate and Upgrade Tissue Packaging Line
Project started in October 2005 - Project completed in February 2006
For this project General Construction moved and upgraded a production line which converts very large rolls of tissue to finished product. |
 |
 |
Scott Worldwide Cogeneration Project
Project started in 1993 - Project completed in 1995
For this project General Construction built a state-of-the-art cogeneration facility primarily for burning spent sulfite liquid from the pulping process and sawdust from area sawmills. |
 |
 |
Substation Replacement & Power System Upgrades
Project started in January 2004 - Project completed in July 2004
General Construction was responsible for building a new substation at paper manufacturing facility. |
 |
 |
Switchgear Relocation
Project started in 2006 - Project completed in 2007
This project included the relocation of a new primary 15kV distribution system and switchgear. |
 |